10. The connectors on the valve cable

(C03) are marked RIGHT UP, LEFT
UP
, RIGHT DOWN and LEFT
DOWN
. Cables labeled with UP go
on the same side as the hydraulic hoses.

Figure 32: Valve Cable Connections

11. Connect the CAN Node cable (C02B)

to the 4-pin AMP plug on C11.

12. Route the CAN Node cable (C02B) to

the roll sensors which are installed in
Section 1.1. Follow existing cables
and/or hydraulic lines.

13. Connect 4-pin AMP connectors on

C02B to the sensors. Connect the
sensor branch cable (C02) to the 4-pin
AMP plug on C02B (Figure 33).

Figure 33: Cable Configurations: C01,

C02, C02B, C03 and C04

14. Route the sensor branch cable (C02) to

the wing and main sensors and connect
to the sensors. Follow existing cables
and/or hydraulic lines along the boom.

15. Cable-tie the installed cables every 12

inches.

IMPORTANT:

Provide enough slack in all cables to
account for the movement of the
main section, parallel lift, and
FOLDING boom movement.