AIR CONDITIONER INSTALLATION

General Information
The S5BP series air conditioner is designed only for
outdoor rooftop or ground level installations. This unit has
been tested for capacity and effi ciency in accordance
with A.R.I. Standards and will provide many years of safe
and dependable comfort, providing it is properly installed
and maintained. Abuse, improper use, and/or improper
maintenance can shorten the life of the appliance and
create unsafe hazards.

To achieve optimum performance and minimize equipment
failure, it is recommended that periodic maintenance be
performed on this unit. The ability to properly perform
maintenance on this equipment requires certain
mechanical skills and tools.

Before you install this unit

 The cooling load of the area to be conditioned must be

calculated and a system of the proper capacity selected.
It is recommended that the area to be conditioned be
completely insulated and vapor sealed.

 Check the electrical supply and verify the power supply

is adequate for unit operation. The system must be wired
and provided with circuit protection in accordance with
local building codes. If there is any question concerning
the power supply, contact the local power company.

 The indoor section (air handler, furnace, etc) should be

installed before routing the refrigerant tubing. Refer to
the indoor unit's installation instructions for installation
details.

 All units are securely packed at the time of shipment and

upon arrival should be carefully inspected for damage
prior to installing the equipment at the job site. Verify
coil fi ns are straight. If necessary, comb fi ns to remove
fl attened or bent fi ns. Claims for damage (apparent or
concealed) should be fi led immediately with the carrier.

 Please consult your dealer for maintenance information

and availability of maintenance contracts. Please read
all instructions before installing the unit.

Locating the Air Conditioner
• Survey the job site to determine the best location for

mounting the outdoor unit.

• Overhead obstructions, poorly ventilated areas, and

areas subject to accumulation of debris should be
avoided.

• Suffi cient clearance for unobstructed airfl ow through the

outdoor coil must be maintained in order to achieve rated
performance. See Figure 2 for minimum clearances to
obstructions.

• Consideration should be given to availability of electric

power, service access, noise, and shade.

18"

18"

18"

18"

TOP OF UNIT

TO BE

UNOBSTRUCTED

Figure 2. Clearance Requirements

Rigging and Hoisting

WARNING:

To avoid the risk of property damage, personal
injury, or death, it is the rigger’s responsibility
to ensure that whatever means are used to hoist
the unit are safe and adequate:

The lifting equipment must be adequate for the
load. Refer to Table 3 (page 12) for unit weights.

The unit must be lifted from the holes in the
base rails using cables or chains.

Spreader bars are required to protect the unit
and ensure even loading.

Keep the unit in an upright position at all times.

All panels must be securely in place during
rigging and hoisting.

Rooftop
Rooftop installations must be located according to local
building codes or ordinances and these requirements:
• Units may be installed on Class A, B, or C roof covering

material. The roof must be capable of handling the
weight of the unit. For unit weights, see Table 3 (page
12). Reinforce the roof if necessary.

• Secure optional mounting pad or frame to roof using

acceptable mechanical methods per local codes.

Packaging Removal
Locate and remove all screws securing the unit to the
shipping skid. NOTE: To prevent damage to the tubing
connections, carefully remove the carton and user’s
manual from the equipment. Discard the shipping carton.