background image

INSTALLATION

Section 7 - Post Installation

PRIMEPACT 70G and 70LP Recreational Vehicle Generators

7.5

INSTALLATION CHECKLIST

♦ LOCATION AND SUPPORT________________________

U Generator is properly located.

J Generator is properly supported.

□ Generator is properly restrained.

♦ GENERATOR COMPARTMENT______________________

□ Compartment construction is proper.

□ Holes/Openings are vapor-sealed.

□ Compartment size is correct.

□ Compartment is vapor-sealed.

□ Sound insulation is correct.

□ Floor cutouts are properly completed.

♦ COOLING AND VENTILATING AIR___________________

□ Airflow is adequate.

□ Air inlet opening is correct.

□ Compensate for restrictions.

□ Check that installation has been tested.

♦ GASOLINE FUEL SYSTEM________________________ _

□ Fuel tank complies with all applicable codes.

□ Fuel system is properly installed and checked

for leaks.

♦ OPTIONAL LP GAS

FUEL

SYSTEM_________________

□ Fuel system is properly installed and checked

for leaks.

□ Pressure at regulator inlet is correct.

□ Rated flow of primary regulator is correct.

□ All parts are properly installed.

□ Fuel system is properly tested/adjusted.

♦ EXHAUST SYSTEM

□ Exhaust system complies with all applicable codes.

□ Exhaust system is properly and safely installed.

♦ ELECTRICAL CONNECTIONS

□ Connections comply with local code requirements

and all National Electrical Codes.

□ Junction box is properly installed.

□ Wiring meets all standards.

□ All connections are correct.

□ Conduit is properly installed and sealed.

□ Generator is properly bonded to the vehicle.

♦ BATTERY INSTALLATION

□ Recommended battery is installed.

□ Recommended cables are installed.

□ Cables are clean and tight.

□ Cables are connected properly.

□ Proper ventilation is provided.

□ Terminals are coated with anti-corrosion grease, and

terminal covers are positioned.

♦ OPTIONAL ACCESSORIES

□ Check that remote starRstop panels (if used) are

installed properly.

□ Check that hourmeter kit (if used) is installed

properly.

□ Check that any other options and accessories (if

used) are Installed properly.

♦ POST INSTALLATION TESTS

□ Check that all tests are completed properly.

DATE OF INSTALLATION

NAME OF INSTALLER

SIGNATURE OF INSTALLER