5 Commissioning

5.3 Commissioning checklist

Fill in the commissioning checklist, refer to section 6.

5.4 Benchmark

GB: It is a requirement that the “Benchmark” Installation,

Commissioning and Service Record is completed and left with

the user. This is supplied with the Glow-worm ‘Flurocyl’ range

of cylinders.
IE: it is necessary to complete a “Declaration of Conformity” to

indicate compliance to I.S.813. An example of this is given in

the current edition of I.S.813.

5.5 Hand over to the householder

l

Hand over all manuals to the householder.

l

Advise the householder to keep the manuals near to the

system.
l

Draw special attention to the safety instructions which the

householder must follow.
l

Review the user instructions with the householder and

answer any questions.
l

Show the householder how to operate the solar control, CH

control and any separate DHW control.
l

Inform the householder that the cylinder temperature is

factory set at 65°C and that the DHW temperature can be
adjusted using the TMV by the installer.
l

Inform the householder that the immersion heater is

intended as a standby device and should not be used
simultaneously with the boiler to heat the cylinder.
l

Inform the householder that they are not permitted to

change the settings made on the solar system.
l

Inform the householder that to ensure the continued

efficient and safe operation of the solar system it is
recommended that it is checked and serviced at regular
intervals. The frequency of servicing will depend upon the
installation conditions and usage, but in general, once a year
should be enough.
l

Inform the householder that the boiler and solar cylinder

should be serviced by a qualified engineer annually.
Leave these instructions and the “Benchmark” Installation,

Commissioning and Service record document with the user.