General

Dielectric testing, operational testing, and periodic testing are described in the following paragraphs.

Dielectric Test

In accordance with IEC 255-5 and IEEE C37.90-2005, one-minute dielectric (high potential) tests may be

performed as follows:

•

All circuits to ground: 2,828 Vdc or 2,000 Vac

•

Input to output circuits: 2,828 Vdc or 2,000 Vac

Output contacts are surge protected.

Operational Test Procedure

The following procedures verify operation of relays BE1-50/51B-214/-215/-223 (5 ampere model) and

BE1-50/51B-225 (1 ampere model). The test setup of Figures 5-1 and 5-2 (BE1-50/51B-214/-225) are

intended primarily as an illustration of the principles involved. The BE1-50/51B-215 is illustrated in Figures

5-3 and 5-4. The BE1-50/51B-223 is illustrated in Figures 5-5 and 5-6. Other test setups known to be

capable of testing with the stated and implied tolerances (including equipment specifically designed for

testing relays) may be used.

Test Equipment Required

•

Current source with a range from 0 to 20 Aac (sensing input current)

•

AC or DC voltage source (target operation)

•

Timer or counter

CAUTION

To ensure proper timing during testing, before each test, remove the current

from the unit for R times D seconds (refer to Section 1, Specifications, Time

Reset for R and D definitions).

Figure 5-1. Pickup and Timing Test Setup, BE1-50/51B-214/-225

BE1-50/51B-214/-225

6

5

3

1

TIME

INST

2

CURRENT

SOURCE

INPUT

STOP

TIMER

START

AMPS

TEST SET