Daktronics BB-2102 Tuff Sport Four-Sided Basketball LED Scoreboard User Manual

Page 20

Advertising
background image

14

Mechanical Installation

If the scoreboard is to be suspended from a hoist:

1. Attach the cable sling to the four lift tubes on the corner braces of the frame.
2. Lower the hoist cables and attach them to the master links.
3. Raise the scoreboard 1-2' (305-610 mm) from the floor, and level the scoreboard by

adjusting the turnbuckles built into the slings.

4. The hoist installer must set upper and lower primary limits and all safety limits.

Daktronics recommends maintaining a minimum of 2' (610 mm) between the
scoreboard and the nearest obstruction.


WARNING! Never raise or lower the scoreboard with personnel or equipment underneath!