6.2.2

Periodic inspection (six monthly)

a)

Check foundation bolts for

security of attachment and corrosion.

b) Check pump running records for hourly usage to

determine if bearing lubricant requires changing.

c) The coupling should be checked for correct

alignment and worn driving elements.

d)

Refer to the manuals of any associated

equipment for periodic checks needed.


6.2.3

Re-lubrication

For general guidelines refer to section 5.2.5,
Lubrication schedule.

Lubricant and bearing temperature analysis can be
useful in optimizing lubricant change intervals.

6.2.4

Mechanical seals

When leakage becomes unacceptable the seal will
need replacement.

6.2.5

Gland packing

The stuffing box is normally supplied with a lantern ring
to enable it to be lubricated to the centre of the packing
with the required Molykote 44 Medium or equivalent
grease from a Staufer or equivalent.

6.3 Spare parts


6.3.1

Ordering of spares

Flowserve keeps records of all pumps that have been
supplied. When ordering spares the following
information should be quoted.

1)

Pump serial number.

2)

Pump size.

3)

Part name – taken from section 8.

4)

Part number – taken from section 8.

5)

Number of parts required.


The pump size and serial number are shown on the
pump nameplate.

To ensure continued satisfactory operation,
replacement parts to the original design specification
should be obtained from Flowserve. Any change to
the original design specification (modification or use
of a non-standard part) will invalidate the pump’s
safety certification.

6.3.2

Storage of spares

Spares should be stored in a clean dry area away
from vibration. Inspection and re-treatment of
metallic surfaces (if necessary) with preservative is
recommended at 6 monthly intervals.

6.4 Recommended spares

(For two years operation - as per VDMA 24296)

Number of pumps

(including stand-by)

Part

no.

Designation

2

3

4

5

6/7

8/9

10(+)

2100

Shaft

1

2

3

30%

2200

Impeller

1

2

3

30%

3011

Radial ball bearing

1

2

3

4

50%

3013

Bearing - thrust

1

2

3

4

50%

3712

Bearing nut

1

2

3

4

50%

4120

Lantern halves #

1

2

3

30%

4130

Gland packing -
complete set #

2

3

4

40%

4200

Mechanical seals # 1

2

3

30%

4305

Lip seal #

4

6

8

9

10

100%

4590.1 *

Pump casing
gasket

4

6

8

9

12

150%

4590.3

Discharge flange
gasket

4

6

8

9

12

150%

4590.2

Impeller gasket

4

6

8

9

12

150%

4610.1

O-ring carrier

2

3

4

50%

4610.3

O-ring soleplate#

2

3

4

50%

-

Power end

-

-

-

-

-

1

2

# When required due to fitting as part of the original build specification.

6.5 Tools required

A typical range of tools that will be required to
maintain these pumps is listed below.

Readily available in standard tool kits, and dependent
on pump size:

Open ended spanners (wrenches) to suit up to
M 48 screws/nuts

Socket spanners (wrenches), up to M 48 screws

Allen keys, up to 10 mm (A/F)

Range of screwdrivers

Soft mallet


More specialized equipment:

Bearing pullers

Bearing induction heater

Dial test indicator

C-spanner (wrench) - for removing shaft nut.
(If difficulties in sourcing are encountered, consult
Flowserve.)

6.6 Casing, seal housing and fastener

torques

Fastener

Screw size

Torque Nm (lbf ft)

All except where
otherwise stated

M8

M10
M12
M16
M20

16 (12)
25 (18)
35 (26)
80 (59)

130 (96)