2.3 Position the P-200 cartridge gland with the gland gasket in place

against the pump back plate (seal chamber/stuffing box) face,

install flat washers on the studs to prevent misalignment, and

tighten the gland nuts evenly, cross-staggering the adjustment

of the nuts. Do not over tighten.

2.4 Assemble the pump, adjust the bearings, set the impeller

and connect the coupling so that the shaft is in its operating

axial position. Any subsequent axial adjustment of the shaft

requires resetting of the seal. Connect pump piping,

(see Section 3) allowing no pipe strain on the pump casing.

2.5 Tighten the set screws on the P-200 cartridge collar with the Allen

wrench provided.

2.6 Remove setting devices by removing the cap screws with the

Allen wrench provided. Save the setting devices for use if pump

impeller must be reset or if the P-200 is removed for maintenance.

2.7 Turn the shaft by hand to ensure free operation.
2.8 Pipe up the gland connections to the P-200 seal as explained in

Section 3.

2.9 See Operational Recommendations, Section 4, before starting

pump.

3 Piping

3.1 Install an ANSI 7311 flush for horizontal pumps or ANSI 7313

for vertical pumps. from the pump discharge to the P-200 seal

flush port,

a

Figure 4. To maximize seal life, Flowserve recom-

mends a product bypass flush be used whenever possible with a

P-200 seal installed in conventional stuffing box. A bypass flush is

not necessary when an enlarged tapered or cylindrical seal cham-

ber is used. If a bypass flush is not used, plug the flush port

a

.

Advertising