Flowserve 191400 Series User Manual

Page 7

Advertising
background image

7

Figure 2

9

COMMISSIONING

CAUTION: Ensure that no foreign particles are present

in the line system

9.1

Idle test

Operate valve once by actuating with compressed air,

while checking mechanical function of valve.

• TC clamp (4) seated tightly

• Check air pressure and air connections for leakage

• Check stroke path; valve spindle (3) should open

and close without jerking

Check function of the actuator based on documenta-

tion for actuator.

Clean system before operating with product for the

first time.

9.2

Test Run under Operating Conditions

Check sealing elements for leakage.

Replace defective seals as described in installation and

removal instructions.

Check mechanical functions (see idle test).

Check function of control drive (see idle test).

9.3

Initial Operation

Check valve function analog to test criteria for test run.

9.4

Malfunctions

Eliminate any malfunctions, which occur immediately

according to installation and removal instructions.

9.5

Malfunctions

Eliminate any malfunctions, which occur immediately

according to installation and removal instructions.

10

MAINTENANCE

Before maintenance

CAUTION:

Valves with air-to-open actuators: tension the actua-

tor springs using top handwheel or by applying sup-
ply air under the membrane.

Failure to do this will cause the valve bonnet to

spring-out when the clamp is released due to the

spring pressure acting between the plug and seat.

Observe electrical connection voltage, as necessary

switch off power supply.

Have repair work performed only by trained personnel

authorised by the operator.

Plug/stem (3)

Wiper (5)

PTFE-guide(8)

TC-clamp (4)

Bonnet (2)

O-Ring, body seal (6)

O-Ring, Stem seal (7)

Valve body (1)

Advertising