Installation – Flowserve NRG 16-51 User Manual
Page 16
6
Installation
NRG 16-51, NRG 17-51, NRG 19-51, step 1
. Screw electrode tip 4 into measuring electrode 1.
Fig. 7
. Carefully determine required measuring length of electrode.
3. Mark length of electrode tip 4.
4. Unscrew electrode tip 4 from measuring electrode 1 and cut tip.
5. After visual inspection screw electrode tip 4 into measuring electrode 1. Slide spring 3 along
electrode tip 4 so that its end completely enters the small hole 2.
NRG 16-51, NRG 17-51, NRG 19-51, step 2
6. Check seating surfaces.
Fig. 10
7. Place joint ring 5 onto seating surface 6 of the electrode.
Fig. 8
8. Apply a light smear of silicone grease (e. g. WINIX
®
50) to electrode thread 7.
9. Screw level electrode into threads or flange provided on vessel and tighten with a 4 mm
open-end spanner.
The torque required
when cold is 160 Nm.
NRG 16-50F, NRG 17-50F, NRG 19-50, additional information
One level electrode NRG ...-5 F can be installed together with one GESTRA level electrode (with
aluminium terminal box) in a single protection tube or external level pot.
Please proceed as follows:
. Mount level electrode NRG ...-5F as first device as described in items 6 – 9.
When installing level electrode NRG ...-5 F, please observe the following instructions:
. Unscrew screws
g
and remove housing cover
i
.
Fig. 12. The arrow on the name plate points
towards this cover.
. Loosen nut
j
with a 9 mm spanner, but do not remove!
Fig. 13
3. Turn terminal box into desired position (+/– 80°).
The terminal box can now be turned through +/– 180° .
4. Tighten nut
j
with a torque of
25 Nm.
5. Mount housing cover
i
and tighten screws
g
.
Note
n
One level electrode NRG ...-5 can be installed together with one GESTRA water
level limiting electrode in a single protection tube or external level pot (inside diameter
00 mm).
Fig. 16.