Installation – Flowserve NRG 16-51 User Manual

Page 17

Advertising
background image

7

Note

n

For the approval of the boiler standpipe the relevant regulations must be considered.

n

Refer to pages 8 for typical installation examples.

n

The angle of inclination of the electrode must not exceed 45°, with the length of the

electrode rod being limited to 000 mm.

Fig. 15

n

For outdoor installations please use level electrode NRG ...-5 F. Level electrodes with

this suffix (F) feature a terminal box made from aluminium.

n

The seating surfaces of the standpipe or the flange provided on the vessel must be

accurately machined, see

Fig. 10

n

Do not bend electrode tip when mounting.

n

Use only the joint rings supplied with the electrode.

NRG 6-5, NRG 7-5, NRG 9-5: 7 x 3, form D, DIN 7603, .430

n

Do not lag electrode body above the hexgonal section.

n

Do not insulate electrode thread with hemp or PTFE tape!

n

Do not apply conductive paste or grease to the electrode thread!

n

Make sure that the air distance between the electrode rod and earth (flange, vessel

wall) is not less than 4 mm.

Fig. 14 – 17

n

Observe the minimum distances for the installation of the electrode!

Attention

Tools

n

Open-end spanner A. F. 3, DIN 30, ISO 338

n

Open-end spanner A. F. 9, DIN 30, ISO 338

n

Open-end spanner A. F. 4, DIN 30, ISO 338

n

Scriber

n

Hacksaw

n

Flat file, medium cut, DIN 76, form A

Installation

– continued –