Installation – Flowserve NRG16-12 User Manual

Page 12

Advertising
background image

2

Attention

The seating surfaces and threads on the vessel and mounting flange must be accurately

machined,

Fig. 9

Use GESTRA PN 60 hat flange when applying the equipment in a high-pressure steam

boiler.

Do not bend the electrode tip when cutting.

Use only the supplied ring joint 27 x 32, form D, DIN 7603, .430, bright-annealed.

Do not lag the electrode body.

Do not insulate the threads with hemp or PTFE tape.

Do not apply conductive paste or grease to the electrode thread.

Provide a min. spacing of 4 mm between electrode and earth (flange, boiler wall),

Fig. 11, Fig. 12, Fig. 13, Fig. 14

Observe the minimum distances for the installation of the electrode,

Fig 14

Installation

NRG 1...-12, step 1

. Screw electrode tip

D

into measuring electrode

A

,

Fig. 6

2. Carefully determine required measuring length, taking minimum length into account.
3. Mark length of electrode tip

D

.

4. Unscrew electrode tip

D

from measuring electrode

A

and cut tip.

5. Screw electrode tip

D

into measuring electrode

A

and tighten. Slide spring

C

along electrode tip

D

, so that its bent end completely enters into small bore

B

.

6. If a measuring surface extension is required slip disk

E

onto electrode tip

D

ensuring that the

electrode tip protrudes 2 mm from the bottom of the disk. Fasten disk with set screw

G

.

Push star-lock washer

F

over electrode tip against disk.

NRG 1...-12, step 2

. Check seating surfaces,

Fig. 9

2. Place joint ring

H

onto seating surface

I

of electrode,

Fig. 7

3. Apply a light smear of silicone grease (e. g. Molykote

®

) to electrode thread

J

.

4. Screw level electrode into threads of flange provided on vessel and tighten with a 36 mm ring

spanner. The torque required is

160 Nm when cold.

Molykote

®

 is a registered trademark of DOW Corning Corp., Midland Michigan, USA