INSTALLATION

Continued

CHECkING GAS CONNECTIONS

WARNING: Test all gas piping

and connections, internal and

external to unit, for leaks after

installing or servicing. Correct

all leaks at once.

WARNING: Never use an

open flame to check for a leak.

Apply a noncorrosive leak detec-

tion fluid to all joints. Bubbles

forming show a leak. Correct all

leaks at once.

PRESSURE TESTING GAS SUPPLY
PIPING SYSTEM
Test Pressures In Excess Of 1/2 PSIG
(3.5 kPa)
1. Disconnect log set and its individual equip-

ment shutoff valve from gas supply piping
system.

2. Cap off open end of gas pipe where equip-

ment shutoff valve was connected.

3. Pressurize supply piping system by either

using compressed air or opening main gas
valve located on or near gas meter.

4. Check all joints of gas supply piping sys-

tem. Apply a noncorrosive leak detection
fluid to all joints. Bubbles forming show a
leak.

5. Correct all leaks at once.
6. Reconnect log set and equipment shutoff

valve to gas supply. Check reconnected
fittings for leaks.

Test Pressures Equal To or Less Than
1/2 PSIG (3.5 kPa)
1. Close equipment shutoff valve (see

Figure 5).

2. Pressurize supply piping system by either

using compressed air or opening main gas
valve located on or near gas meter.

3. Check all joints from gas meter to equip-

ment shutoff valve (see Figure 6). Apply
a noncorrosive leak detection fluid to all
joints. Bubbles forming show a leak.

4. Correct all leaks at once.

Figure 6 - Checking Gas Joints

Gas Meter

Equipment
Shutoff Valve

HEARTH KIT ASSEMBLy AND
INSTALLATION

Kit Assembly
Note: The following instructions apply to
both standard single bar burners, as well as
dual flame “U” style burners. Be sure all pipe
threaded connections are tight, and have
thread compound to prevent leaks.
1. Determine which side the gas line will be

coming into the fireplace.

2. Using a hammer and screw driver, remove

knock-out plug from the side of the pan
that corresponds to the gas line (see
Figure 7).

3. Unscrew burner inlet fitting from burner

manifold (see Figure 8, page 9).

4. Place burner manifold in pan with thread-

ed opening facing open knock-out plug.

Figure 5 - Equipment Shutoff Valve

Open

Closed

Equipment
Shutoff
Valve

Knock-out
Plugs

Figure 7 - Knock-Out Plug Locations

Advertising