19 620RE, 620RE4 and 620R Pump installation

A correctly engineered installation will promote the best possible tube life, so please ensure
that the following guidelines are followed:

Avoid tight pipeline bends, pipe reducers and excessive lengths of smaller bore
tubing than that in the pumphead, particularly in pipelines on the suction side.

Ensure that connecting pipe work and fittings are suitably rated to handle the
predicted pipeline pressure.

If rigid pipework comes in close proximity to the pumphead, a drop-out section of
pipework will simplify tube replacement. When using element pumpheads, ensure
that a minimum of 1m of flexible interface pipework is connected between the
pumphead and any rigid pipework.

Ensure that the controlled waste blanking plug is in position if the controlled waste
port is not in use. See below.

It is advisable to use controlled waste pipe work if pumping hazardous, aggressive or
abrasive fluids or products which will harden in contact with air.

When connecting waste pipe work to the controlled waste port using the coupling
adaptor supplied, ensure that there is adequate clearance underneath the pumphead.
Waste pipe work should run to a suitable container or drain.

The leak detector installation procedure is included in the leak detector kit.

If unsure of an installation please contact your local Watson-Marlow Technical
Support Office for further assistance.