8 Commissioning

Installation Manual

TCS-IT-IEN103610

25

8 Commissioning

8.1 Commissioning the Transformer Compact Station

8"3/*/(

Danger of fire if the connection is faulty.

• Switch off all switch elements:

– Switch off the low-voltage switchgear (see the documentation for the low-voltage

switchgear).

– Switch off the medium-voltage switchgear (see the documentation for the medium-voltage

switchgear).

– Remove fuses.
– Open the miniature circuit-breaker.
– Open the residual current device.

Warranty and Guarantee Claims

Warranty or guarantee claims can only be made valid if the initial start-up was carried out by
SMA Solar Technology AG or if the fully completed and signed "Initial Commissioning Report
for Sunny Central Systems" is completed and available at SMA Solar Technology AG. The
commissioning report is included with Sunny Central.