Operating Instructions Powador XP100-HV

Page 15

I n s t a l l a t i o n / S t a r t - u p

Floor

•

Must have adequate load-bearing capacity

•

The building material must meet the require-
ments of building material class B1 (“Flame-
resistant Building Materials”, in accordance with
DIN EN 13501-1)

Room

•

Should be as dry as possible

•

Must be indoors (IP 21)

•

The installation location must be climate-con-
trolled in order to dissipate the waste heat

•

Additional ventilation should be provided, if
necessary

•

Do not install in a room where there is a risk of
explosion

Clearance between walls and ceiling

•

Must be accessible for installation and
maintenance

•

Air circulation may not be blocked (fi gure 6)

•

You do not have to provide for clearance on the
sides or to the rear of the unit

•

Minimum clearance between unit and ceiling:
40 cm

Figure 6: Ventilation for the inverter