Eaton Electrical IM01005012E User Manual

Page 10

Advertising
background image

IM01005012E

XT-40 & IT-RSS Installation

Page 8

Rev. 1 – 2/2007

2.8 Power Up and System Checkout

Apply system power and observe that the LED(s) on the front of the SPD should glow. One LED should
glow for each Phase voltage being monitored.

Should there be a significant difference in brightness, check the phase rotation of the panel and ensure
that the SPD’s Phase wires are connected to the correct phase. Slight differences in brightness DO NOT
indicate a faulty device, rather specification tolerance differences of the indicator circuit’s components.
LED brightness symmetry and/or level do not indicate the SPD’s operational status.