7. connecting work clamp, 8. connecting input power – Hobart Welding Products AIRFORCE ICE-27C User Manual

Page 17

Advertising
background image

OM-203 653 Page 13

4-7. Connecting Work Clamp

802 463-A

1

Work Clamp

2

Workpiece

Connect work clamp to a clean,

paint-free location on workpiece, as

close to cutting area as possible.

1

2

4-8. Connecting Input Power

Ref. 802 787 / 802 786

Check input voltage available at

site.
1

Changeover Switch

Switch is accessible through slot in

rear panel.
2

Changeover Switch Label

Look at label to find correct switch

position.
Y Be sure input power

connection meets all

applicable national,

regional, and local electrical

codes.

3

Grounded 120 VAC

Receptacle

Y To use rated output (see

specifications), connect the

unit to an individual branch

circuit capable of carrying

the effective (eff) current for

the output being used. The

unit must have a properly

sized plug installed and the

circuit must be protected by

properly sized fuses or cir-

cuit breakers.

A 120 volt, 20 ampere individual

branch circuit protected by

time-delay fuses or circuit breaker

is required (see Section 4-1).
4

Plug From Unit

Select extension cord of 12 AWG

for up to 53 ft (16 m).
5

Grounded 230 VAC

Receptacle

A 230 volt, 10 ampere individual

branch circuit protected by

time-delay fuses or circuit breaker

is required (see Section 4-1).
6

Plug From Unit (Customer

Supplied)

Select extension cord of 14 AWG

for up to 133 ft (41 m).
Y Special installation may be

required where gasoline or

volatile liquids are present −

see NEC Article 511 or CEC

Section 20.

4

3

5

6

2

1

Advertising