For Vertical Runs
The flue system must be supported every eight
(8) feet (2.4M) above the heater flue outlet by wall
brackets.

To install support brackets for vertical runs:
• Attach wall brackets to the flue pipe and se-

cure the wall bracket to the framing members
with nails or screws.

Use wall brackets to support vertical runs every
8 feet (2.4M) above the heater flue outlet.

Figure 13 Installing Support Brackets

4. Install Firestops

For Horizontal Runs - Firestops are REQUIRED
on both sides of a combustible wall through which
the flue passes.

To install firestops for horizontal runs that pass
through either interior or exterior walls:

• Cut a 12-inch by 12-inch (305 mm X 305 mm)

hole through the wall. The center of the hole
is one (1) inch (25mm) above the center
of the horizontal flue pipe.

• Position the firestops on both sides of the hole

previously cut and secure the firestops with nails
or screws.

• The heat shields of the firestops MUST BE

placed towards the top of the hole.

• Continue the flue run through the firestops.

Figure 14 Hole and Flue Pipe

Figure 15 Heat Shield, Interior and Exterior
Firestops

For Vertical Runs - One ceiling firestop is
REQUIRED at the hole in each ceiling through
which the flue passes.

To install firestops for vertical runs that pass through
ceilings:

• Position a plumb bob directly over the center of

the vertical flue component.

• Mark the ceiling to establish the centerpoint of

the flue.

FLUE PIPE

1 INCH MIN.

(25.4mm)

FLUE

OUTLET

WALL BRACKET

WALL STUD

8 FT.

(2.4m)

TRIM HEAT
SHIELD IF TOO
LONG, ADD TO
SHIELD IF TOO
SHORT

EXTERIOR
FIRESTOP

INTERIOR

FIRESTOP

HEAT SHIELD

Advertising