Frymaster SM60 User Manual

Page 14

Advertising
background image

DEAN MILLIVOLT GAS FRYERS (NON-CE)

CHAPTER 2: IMPORTANT INFORMATION

2-4

2.5 Pre-Installation (cont.)

C.

Installation Standards

1. INSTALLATION

STANDARDS: Fryer installation must conform with local codes, or in

the absence of local codes, to the appropriate national standards as listed below:

a. U.S. installations must meet:

b. Canadian installations must meet:

American National Standard Institute

CAN 1-B149 Installation Codes

ANSI Z83.11

Canadian Gas Association

American Gas Association

55 Scarsdale Road

8501 E. Pleasant Valley Road

Don Mills, ONT, M3B 2R3

Cleveland, OH 44131

National Electrical Code

Canadian Electric Code c22.1, part 1

ANSI/NFPA #70

Canadian Standards Association

American National Standard Institute

178 Rexdale Blvd.

1430 Broadway

Rexdale, ONT, M9W 1R3

New York, NY 10018

NFPA Standards #96 and #211

National Fire Protection Association

470 Atlantic Avenue

Boston, MA 02110


D. Australian Requirements

To be installed in accordance with AS 5601 / AG 601, local authority, gas, electricity, and any other
relevant statutory regulations.


2.6 Equipment Installed at High Altitudes

1. The fryer input rating [BTU/hr (kW/hr)] is for elevations up to 2,000 feet (610-m). For

elevations above 2,000 feet (610-m), the rating should be reduced 4-percent for each additional
1,000 feet (305-m) above sea level.


2. The correct orifices are installed at the factory if the operating altitude is known at the time of the

customer’s order.






Advertising