On-site quick start – MGE UPS Systems STS 600A User Manual

Page 11

Advertising
background image

Quick Start

QS —1

86-504004-00 B03

On-Site Quick Start

CAUTION

Scheduling of the MGE Field Service Engineers typically should be

done 7 to 10 days before they are required on-site. If the startup of

the UPS is critical to maintaining your schedule, please call the

MGE toll free telephone number at 1-800-438-7373 for assistance.

Final installation and start-up should be completed by a qualified MGE Field Service Engineer.

This On-site Quick Start will guide qualified engineers through unpacking and positioning the unit, the equipment,

tools, and steps required to perform power input/output connections to prepare the unit for MGE Field Service

Engineers to perform on-site final installation and startup.

To insure a successful installation, each of these (4) steps should be followed in their correct sequence.

Note that any unauthorized installation may cause damage to the UPS(s) and void the MGE warranty.

First steps by an on-site qualified Technical Engineer

Step 1.

Unpack and position the unit

Step 2.

Connect the main (utility) power

Step 3.

Connect the output to the power distribution panel

Step 4.

The MGE Field Service Engineer finalizes installation and the startup process.

Optional :

Procedure for temporary power prior to the final startup.

Required Equipment and Tools

The following equipment and tools are recommended for on-site installation:

Digital volt meter (DVM)

1/8 inch slotted screwdriver

Pallet jack/forklift

Conduit installation tools

Nut driver set