Initial starting procedure – SPX Cooling Technologies MARLEY CLASS 800 User Manual

Page 7

Advertising
background image

7

Initial Starting Procedure

1— Fill the cold water basin and circulating water system to a level 1/2”

(13 mm) below the overflow.

2— Bypass valve should be closed unless start-up is in cold weather. (See

Routine Starting Procedure on page 8.)

3— Prime and start the circulating water pumps one at a time. Increase the

flow of circulating water gradually to design water rate to avoid surges
or water hammer which could damage the distribution piping.

4— When flow has stabilized at or near the design rate, adjust water make-

up to maintain the level that the water has pumped down to in the cold
water basin. (See Cold Water Collection Basin on page 10.) This
should coincide reasonably with the recommended operating water level
indicated on the Marley project drawings.

5— Start the fan(s). After 30 minutes operating time, to permit Geareducer oil

to come up to operating temperature, check motor load with watt meter, or
take operating volt and ampere readings and calculate motor horsepower.
Refer to Marley Fan User Manual for instructions.

If it is necessary to adjust fan pitch to pull correct contract
horsepower, measure results when circulating design water rate
at design hot water temperature. Horsepower will change with air
density. Lock out all electrical service before entering fan area.

Caution

Advertising