Octel Unified Messenger Concepts & Planning Guide

2-8

101-1620-005

Total estimated port
requirements

To summarize, when sizing the number of total ports required for any
given server to provide a desired GOS, the following factors must be
considered.

n

Estimated total busy hour offered traffic generated by both
internal and external callers.

n

Estimated total busy hour offered traffic generated by all
applications, including those that place outgoing calls.

A system planner should allow for a safety or growth factor of 5% to 15%
when sizing the initial implementation.