Task 4: connect the ldm port cable, Figure 2-5: ldm port cable connection, Task 4: connect the ldm port cable -8 – Network Technologies 900GV User Manual

Page 28

Advertising
background image

How to Install the Module

2-8 Installing the DIGITAL VNswitch 900GV

Task 4: Connect the LDM Port Cable

To perform a remote dump, the LDM cable must be connected to the LDM port. The
LDM port uses straight-through, 10BaseT, 8-pin MJ connectors.

To connect the LDM port cable to the LDM port (Figure 2-5), complete the following
steps:

Figure 2-5:

LDM Port Cable Connection

Step

Action

1

Align the release tab on the cable plug (1), with the keyway on the
module’s 10BaseT port connector.

2

Insert the plug into the connector, ensuring that the release tab snaps into
the locked position.

NPB-1051-98F

VNswitch 900GV

FD

DI/E

th

ern

et

1

2

Advertising