Toshiba RELIABILITY IN MOTION 1000 User Manual

Page 28

Advertising
background image

5

Planning a UPS system should include the following considerations:
• The total demand of the protected system shall dictate the output power rating (VA).

Allow a margin for future expansion or calculation inaccuracies from measuring

power requirements.

• Backup time needed will determine the battery size needed. If the load is less than

the UPS nominal power rating then the actual backup time will be longer.

• The following options are available:

• External Battery Cabinets, and
• Connectivity options (Remote Contact, SNMP/WEB card).

The following UPS models are available.

Model

Backup time Internal

batteries

Recharge time to 90%

capacity

UPS 1000VA

7 min

4 hours

UPS 1500VA

6 min

4 hours

UPS 2000VA

7 min

4 hours

UPS 3000VA

6 min

4 hours

Additional External Battery Cabinets are available if more back-up time is needed.

Advertising