Plan Your Installation

FIG. 4

12

ABOVE TOP OF

WARM AIR PLENUM

FROM THE

FRONT

FROM SIDES

AND BACK

FROM CHIMNEY

CONNECTOR

6 FT OF

PLENUM

6 FT OF

PLENUM

CLEARANCES TO COMBUSTIBLES

6”

48”

18” *

18”

6”

1”

!

!

CAUTION

BE SURE TO INSTALL DUCT WORK

WITH CLEARANCES SHOWN

Floor Joist or Combustible Material

FURNACE

WARM AIR

PLENUM

6 Inches

6 Feet

Heat Supply

Ducts

1”

1” CLEARANCE TO
COMBUSTIBLES
BEYOND 6’ TO A
POINT WHERE
THERE IS A
CHANGE IN
DIRECTION OF
90 DEGREES OR
MORE.

Top View

Top View

Warm Air

Plenum

Cold Air

Plenum

18” MIN

18” MIN

8” Dia.

Flue Pipe

Combustible

Walls

NOTE:
DUCT AND PLENUMS SHALL BE
CONSTRUCTED ENTIRELY OF
SHEET METAL.

* Up to 50% less clearance between combus-
tible walls and chimney connector to furnace
and ducts is allowed if insulated according to
NFPA Standard 90B or your local building
code. This copyrighted book is available from
the National Fire Protection Association, Inc.,
PO Box 9101, Quincy, MA 02269-9101

SERVICE CLEARANCE OF 24 INCHES
MINIMUM REQUIRED TO SERVICE
BLOWER

FLOOR TO BE NON-COMBUSTIBLE MATERIAL