Inst allation - hanging the hood onto the w all – Zephyr CPA-E48ASX User Manual

Page 19

Advertising
background image

19

www.zephyronline.com

Inst

allation - Hanging the Hood onto the W

all

14. For internal blower installation ONLY:

a. Horizontal (Rear) discharge:
Install from the outside the 3 1/4 ” x 10” Rect.
transition on the outlet hole of the blower with 3
screws.
b. Vertical (Upper) discharge:
Install from the outside the 8" plastic round
transition, with 4 screws. Install transition so that
little position adjustment are allowed.
Note: Seal with duct tape only when transition is
firmly attached to the range hood.
Do not use duct smaller than the transition, (see
installation step 9) for further instruction about
duct to be used.

15. Hang hood on lower bracket.

WARNING

Excessive Weight Hazard - Use three or more people
to move and install range hood. Failure to do so can
result in back or other injury.

16. Secure hood with screws and washers.

17. Connect the ducting to the transition. Seal with duct

tape.
Note: If Duct has been already fixed to transition
(See installation step 15b), install the transition to
the hood with 4 screws.
Do not use duct smaller than the transition, see
installation step 9 for further instruction about
duct to be used.

Rear outlet
(Horizontal
discharge)

Upper outlet
(Vertical discharge)

Knock-out junction box (Mains connection)

Knock-out (External Blower connection)

Hanging bracket

Bottom security
screws hole

Bottom security
screws hole

Upper
security
screw
hole

Upper
security
screw
hole

Lower
support
bracket

CenterLine

Rectangular
transition

Advertising