2.6 Extractor fans or cooker hoods must not be placed in the

same room or space as this can cause the appliance to emit

fumes into the room.

2.7 Increase air supply provisions where a room contains multiple

appliances.

2.8 The need for additional ventilation may also be identified

during the commissioning procedure and should be provided

if needed.

An inadequate air supply to the room is potentially

dangerous.

2.9

If any checks reveal problems do not proceed with the

fitting of the appliance until they have been rectified.

PRE-INSTALLATION CHECKS

2.1 Additional ventilation will be required to suit the

requirements of Building Regulations. This must be provided

using a permanently open air vent, of the size listed, which

is positioned so that it is not liable to be blocked both inside

and outside the building.

2.2 The appliance will require additional ventilation as listed*:

A

) Building design permeability greater than 5.0m³ (h.m²).

B

) Building design permeability less than 5.0m³ (h.m²).

Model

YM-CL8HB

A

Additional Ventilation

mm²

4400

cm²

44.00

in²

7.10

B

Additional Ventilation

mm²

7150

cm²

71.50

in²

11.54

2.3 Permanent air vents should be non-adjustable and positioned

where they are unlikely to be become blocked.

2.4 If vents open into adjoining rooms or spaces there must be an

air vent of at least the same size direct to the outside.

2.5 Site the vents where cold draught is unlikely to cause

discomfort. This can be avoided by placing vents near ceilings

or close to the appliance, see diagram.