4-8

2)

Verify that the “AC OK”, “DC OK”, and green LED are on and

the fan operates on each rectifier.

3)

Wait approximately 10-30 seconds to allow the system to go

through its start-up procedure.

4) Verify that the green LED on the controller panel is on. All

alarm LEDs should be off after all rectifiers are latched in

place and all AC circuit breakers are closed.

5) Using a digital voltmeter to verify that the plant voltage is

approximately 54V, the default factory setting for the

controller.

6)

Turn one the AC power input switch off to verify that the red

alarm LED lights on the controller.

7) For systems with more than one rectifier installed, turn the

second AC input switch off to verify that the FAULT LED

lights on the controller. Clear the alarms by turning the AC

circuit breaker on.

When the system shipped from the factory, normally all the

systems parameters have been configured as the default value.

Contact Hangzhou Huawei-3Com Technology Co., Ltd. if special

setting is needed.

Advertising