4 switch on phase – VEGA VEGASON 65 Profibus PA User Manual

Page 28

Advertising
background image

PE

/ L
/ N

L1 N

1

2

1

2

3

4

BUS

Fig. 23: Wiring plan, double chamber housing
1

Power supply

2

Signal output

5.4 Switch on phase

After VEGASON 65 is connected to voltage supply or after voltage
recurrence, the instrument carries out a self-check for approx. 30
seconds. The following steps are carried out:

l

Internal check of the electronics

l

Indication of the instrument type, the firmware as well as the
sensor TAGs (sensor designation)

l

Status byte goes briefly to fault value

Then the current measured value will be displayed and the
corresponding digital output signal will be outputted to the cable.

1)

1)

The values correspond to the actual measured level as well as to the set-
tings already carried out, e.g. default setting.