Installing the Phase Sensors (CTs)

Insulating

Barrier

1

/

2

-13

Bolt

CT Post

The CTs must be assembled with their associated
copper bus parts before they can be installed onto the
breaker frame in the spaces previously occupied by the
electromechanical trip devices.

1. Slide the CT over the post on the lower copper bus

strap, as shown in Figure 7. Place the insulating
barrier on the top of the CT.

CT

2. On a DB-50 breaker, place the top bus strap over the

insulating barrier and insert a

1

/

2

-13 x 1

1

/

4

" bolt, with

a flat washer and lock washer, as shown in Figure 9.
Leave the bolt finger tight for now.

Top Bus

Strap

On a DB-25 breaker, place the top bus strap over the

insulating barrier and insert a

3

/

8

-16 x 1

1

/

4

" bolt, with

a flat washer and lock washer, as shown in Figure 9.
Leave the bolt finger tight for now.

Figure 7. Assembling a CT to the bus.

Figure 8. CT assembly for a DB-50 breaker.

Figure 9. CT assembly for a DB-25 breaker.

3

/

8

-16

Bolt

1

/

2

-13

Bolt

8

Advertising