Installing the device – GE Industrial Solutions Power Break II Draw-out 800-4000 Amp Frames User Manual

Page 7

Advertising
background image

Power Break® II Devices

Draw-Out Device Installation

3

Installing the Device

Use the following procedure to install the draw-out device

into the substructure.
1. Attach the Lifting Bar, catalog number TDOLB, by

locating the hooks on the bar beneath the shoulder

studs of the device, as illustrated in Figures 4 and 5.

2. Pull out the substructure rails until they drop into the

horizontal locked position. Lower the device so that

the grooves in the rollers drop over the rails.

3. Make sure the grooves in all rollers straddle the rails,

as illustrated in Figure 6, then remove the Lifting Bar

and push the device into the substructure until it

stops in the

DISCONNECTED

position. Then lift the

rails and push them in to the stored position.

CAUTION: The device must be

OFF

before it is

connected. If the device is charged, press the

ON

button

to close the device contacts, then press the

OFF

button to

open the contacts.

ATTENTION: Le mécanisme doit être à OFF avant qu’il

ne soit embroché. Si le ressort de fermeture de

mécanisme est chargé, fermer les contacts de mécanisme

par action sur le bouton

ON

, puis appuyer sur le bouton

OFF

pour ouvrir les contacts.

4. Engage the

1 2

-inch square end of the racking shaft

with the supplied wrench, catalog number TDORT,

and rotate the shaft clockwise to draw the device into

the

TEST

or

CONNECTED

position, as illustrated in

Figure 7. The compartment position indicator is

shown in Figure 8.

NOTE: If the device does not fit the structure, check the

rejection relationship, illustrated in Figure 8, to verify

that a correctly rated device is being installed. Table 1

lists the correct draw-out substructure for each device

frame.

NOTE: Si le mécanisme ne rentre pas dans le berceau,

vérifier le détrompeur illustré dans les figure 8, qui

empêche l’insertion d’un mauvais calibre de mécanisme.

La Table 1 définis le berceau convenable à chaque taille

de mécanisme.

Figure 4. Lifting Bar attached to a draw-out device for manual lifting.

Figure 5. Lifting Bar attached to a draw-out device for lifting with a

hoist.

Pipe

Lifting Bar

Shoulder

Stud