GE Industrial Solutions 664 Infinity C DC to DC Power System User Manual

Page 10

Advertising
background image

663 / 664E Installation Guide

CC848921016 r02 December 2012

Page 10

Step 8

System Verification and Alarm Extension

Verification

Using the Controller

• Verify that the display screen is illuminated Green

• Verify that no alarms are reported

• Verify status of all converter modules are

communicating properly

• Verify all extended alarms with the Alarm Center.

(see Pulsar Edge Controller Family Product

Manual for alarm extension test)

• Verify that the plant voltage displayed is within ±

0.05V of voltage measured between the charge

bus and DC Return using a calibrated DVM

• A Yellow display indicates the plant is in a Minor

Alarm condition

• A Red Display indicates the plant is in a Major

Alarm condition

NOTE: Alarms will be extended to the Network Alarm

Center during alarm controller based alarm

testing.

Pulsar Edge Controller

Normal Operation

Pulsar Edge Controller

Minor Alarm Condition

Pulsar Edge Controller

Major Alarm Condition

Step 9

Verify Power Plant Set Points

• Using the controller, verify all Power Plant

set points are per customer standards

• See Pulsar Edge Controller Family Product

Manual for additional controller details

Pulsar Edge Controller

Normal Operation

Advertising