663 / 664E Installation Guide

CC848921016 r02 December 2012

Page 8

Step 4

Run and Terminate Alarm Cabling

• Run and terminate alarm cabling
• Jumper settings are available for both

Close on Alarm and Open on Alarm

extensions

• Verify alarm extensions with the Alarm

Center

• See Pulsar Edge Controller Family

Product Manual for additional information

Step 5

Run & Term. Supply and Return Cables


Output cabling

• With GMT fuses and circuit breakers

removed, land all supply and return cabling

at the rear of the system

• Circuit breaker lug landings -

1/4” on 5/8 inch centers

Torque to 240 in-lb

• GMT wire landings –

Strip wire 3/8”

Torque to 13 in-lb

Connectorized

Alarm Cable

connection

Front

Circuit breaker

landing positions

GMT

landing positions