Step 6

Energize Power Plant


Start up

• Remove all converter modules from the power plant if

previously installed

• Insert a single converter and turn on the input breaker

to this converter. This will apply input voltage to the

controller and system load bus.

• The controllers’ self-diagnostic will start within 30

seconds after power has been applied to the load bus

• Normal operation is indicated by the Green illuminated

front display

Pulsar Edge Controller

Normal Operation

Step 7

Install Converter Modules


Module Installation

Insert converter modules

• Converters can be added or removed with the

power plant energized

Status LEDs:

• Normal = Green
• Input Fail = Amber
• Fail = Red

Green during

normal

operation