663 / 664E Installation Guide
CC848921016 r02 December 2012
Page 9
Step 6
Energize Power Plant
Start up
• Remove all converter modules from the power plant if
previously installed
• Insert a single converter and turn on the input breaker
to this converter. This will apply input voltage to the
controller and system load bus.
• The controllers’ self-diagnostic will start within 30
seconds after power has been applied to the load bus
• Normal operation is indicated by the Green illuminated
front display
Pulsar Edge Controller
Normal Operation
Step 7
Install Converter Modules
Module Installation
Insert converter modules
• Converters can be added or removed with the
power plant energized
Status LEDs:
• Normal = Green
• Input Fail = Amber
• Fail = Red
Green during
normal
operation