11) Place the top hook [1] between side plates A [11] and B [13]. Then insert top pin [4] and fix it with

the split pin [5].

For Bullard , Shur-loc , or Inspection type hooks, refer to Table 6-3 for yoke nut

torque specifications.



:

Always bend the split pin securely after inserting it into the top pin.

Figure 6-5 Gear Train Assembly

12) Place the hand wheel [40] side upward.

13) Reeve the load chain [47] turning the pinion clockwise through the space between the left (bottom

hook side) guide roller [20] and the load sheave [14]. See figure 6-6.



:

Put the welded part of the vertical chain link outward and reeve it through the

load sheave. Pull it out between the right guide roller (no load side) and the load sheave.

For 10 ton capacities and above, pass the no load end of the chain through the cross guide [53].

*NOTE: It is recommended for this process to position the unit so that the side plate A [11] faces left
and the side plate B [13] faces right.