Hardware installation, Power protection, Chapter 3 – Brocade Mobility RFS9510 Controller Installation Guide User Manual
Page 13
Brocade Mobility RFS9510 Controller Installation Guide
9
53-1002918-01
Chapter
3
Hardware Installation
Power protection
•
If possible, use a circuit dedicated to data processing equipment. Commercial electrical
contractors are familiar with wiring for data processing equipment and can help with the load
balancing of these circuits.
•
Install surge protection. Be sure to use a surge protection device between the electricity source
and the Mobility RFS9510 Controller.
•
Install an Uninterruptible Power Supply (UPS). A UPS provides continuous power during a
power outage. Some UPS devices have integral surge protection. UPS equipment requires
periodic maintenance to ensure reliability. A UPS of the proper capacity for the data processing
equipment must be purchased.
Hardware installation
The following sections describe the hardware installation for the Mobility RFS9510 Controller:
CAUTION
A Mobility RFS9510 Controller requires a two man lift. Use all appropriate cautions.