Chapter 3
________________________________________________________________________

________________________________________________________________________

BE1285-15

1309 Multipoint Sampler

LumaSense Technologies A/S

Page 22 of 42

All tasks performed by the 1309 are controlled over the IEEE/IEC inter-

face from a System Controller; there is no other control possibility. This
chapter deals with the control of the 1309 from the user’s point of

view; for details of the IEEE/IEC interface specifications, refer to

Chap-

ter 4

of this manual.

Sections 3.1

and

3.2

deal with switching-on and the general principles

of controlling the 1309.

Sections 3.3

to

3.7

deal with the specific com-

mands and requests, known as interface jobs, which set-up and control

the 1309. Each interface job is dealt with by giving an example which
states the effect of the job. For quick reference, an overview of all in-

terface jobs is given in

section 4.2

of this manual.

3.1 Switching-On

The 1309 can be switched on using the AC Mains switch on the back-
plate. After switching-on, the 1309 is set as follows:

The sampling-valves closed.

Internal three-way valve set to Waste Air Outlet.

3.2 General Principles of Controlling the 1309

The 1309’s functions are controlled over the IEEE/IEC interface using a
range of commands and data requests, each of which is specific to a

particular function or item of data. These commands and requests are
known as interface jobs. This section describes the structure of the in-

terface jobs used to control the 1309. Further details about the
IEEE/IEC interface of the 1309 are given in

Chapter 4

of this manual.

3.2.1

Syntax for Interface Jobs

Fig.3.1 shows a diagram representing a single interface job, sent from

the system controller to the 1309. Each constituent part of the interface
job is explained below.