Operation, General, Filling – American Water Heater (A)BCG3 85T500-8N User Manual

Page 23: Sequence of operation, General filling

Advertising
background image

23

Board waits 3 seconds and then shuts off power to the Silicon

Nitride Ignitor.

11. From the time the Silicon Nitride Ignitor’s power is shut off,

the Ignition Control Board waits 3 more seconds to monitor

the Flame Sensor.

12. If the Flame Sensor does not detect a strong enough flame,

the Ignition Control Board shuts off the Gas Valve and allows

the exhaust Inducer to purge the unit for 20 seconds. At that

time, the Ignition Control Board restarts with step 7. It will try

and ignite the main burners 2 more times. If the unit does not

light, the Ignition Control Board will wait one hour and then

restart at step 3. This cycle will continue until the unit lights

or the power is shutoff to the unit.

13. If the Flame Sensor detects a strong flame, the Ignition Control

Board will allow the unit to operate until the thermostat is

satisfied.

14. Once the unit is satisfied, the Ignition Control Board will shut

off the Gas Valve and the unit will be in standby mode until

another call for heat is initiated by the thermostat.

See the flow chart on page 32 for more information.

The following information will describe the Sequence of Operation

for this appliance.
1. Switch power on to unit.
2. Thermostat calls for heat.
3. Ignition Control Board performs diagnostic check on system

components.

4. On completion of diagnostics check, the Ignition Control Board

sends signal to exhaust Inducer.

5. exhaust Inducer begins drawing air through appliance closing

the Prover Switch.

6. On completion of Prover Switch engagement, the Ignition

Control Board begins the ignition cycle.

7. The Ignition Control Board provides power to the Silicon

Nitride Ignitor.

8. The Silicon Nitride Ignitor heats up for approximately 17 to

20 seconds.

9. At the end of Silicon Nitride Ignitor’s warm-up, the Ignition

Control Board opens the Gas Valve.

10. From the time the Gas Valve opens, the Ignition Control

important

A qualified person must perform the initial firing of the heater. At

this time the user should not hesitate to ask the individual any

questions which they may have in regard to the operation and

maintenance of the unit.
An Operational Checklist is included on page 33 of this manual.

By using this checklist the user may be able to make minor

operational adjustments and avoid unnecessary service calls.

however, the user should not attempt repairs which are not listed

under the USer column.

general

NeVer OPerATe The heATer WIThOUT FIrST BeING

CerTAIN IT IS FILLeD WITh WATer AND A TeMPerATUre

AND PreSSUre reLIeF VALVe IS INSTALLeD IN The

reLIeF VALVe OPeNING OF The heATer.
ShOULD OVerheATING OCCUr Or The GAS SUPPLy FAIL

TO ShUT OFF, TUrN OFF The MANUAL GAS CONTrOL

VALVe TO The APPLIANCe.
Before proceeding with the operation of the unit make sure

the water heater and system are filled with water and all air is

expelled.

filling

1. Close the heater drain valve by turning handle clockwise.
2. Open a nearby hot water faucet to permit the air in the system

to escape.

3. Fully open the cold water inlet pipe valve allowing the heater

and piping to be filled.

4. Close the hot water faucet as water starts to flow.
5. The heater is ready to be operated.

operation

The GAS VALVe MUST hAVe BeeN IN The OFF POSITION

FOr AT LeAST 5 MINUTeS. This waiting period is an

important safety step. Its purpose is to permit gas that may

have accumulated in the combustion chamber to clear. IF yOU

DeTeCT GAS ODOr AT The eND OF ThIS PerIOD DO NOT

PrOCeeD WITh LIGhTING. reCOGNIZe ThAT GAS ODOr,

eVeN IF IT SeeMS WeAk, MAy INDICATe PreSeNCe OF

ACCUMULATeD GAS SOMePLACe IN The AreA WITh

rISk OF FIre Or eXPLOSION. See The FrONT PAGe FOr

STePS TO Be TAkeN.
All gas and water lines must be leak tested and open.
read SeQUeNCe OF OPerATION section of this manual prior

to lighting and operating this appliance.
With above conditions satisfied, start the unit in accordance with

the instructions on the operating label attached to the heater. For

your convenience a copy of the instructions are shown on page

24. each heater is equipped with an ignition control board. The

controller will try three times to light the main burner before going

into lockout. After the controller tries three times, it will wait one

hour before trying to light the unit again. This cycle will continue

until the main burners are ignited or the unit is shut down.
adjustments
ON INITIAL STArTUP SOMe ADJUSTMeNTS Are NeCeSSAry.
1. CheCk MANIFOLD AND INLeT GAS PreSSUreS.
2. CyCLe CheCk - CheCk AT LeAST ONe BUrNer

OPerATION - WheN TherMOSTAT IS SATISFIeD,

BUrNer WILL ShUT OFF AND INDUCer WILL STOP

rUNNING. ON CALL FOr heAT - The INDUCer WILL

COMe ON AND CLOSe The PreSSUre SWITCh AND The

IGNITION SeQUeNCe DeSCrIBeD ABOVe WILL BeGIN,

See “SeQUeNCe OF OPerATION”.

seQuence of operation