1000 Series Granulators

Chapter 3: Installation

19 of 45

3-3 Electrical Connections

Check serial tag voltage/amperage requirements and make sure your electrical service
conforms before making any electrical connections. Make sure that all three phases are wired
correctly.

Bring properly sized power leads and grounds from a fused disconnect to the unit. Provide
external overcurrent protection to the unit, using circuit breakers or fuses. If you use fuses,
make sure that they are dual-element, time-delay fuses, sized according to your electrical
code. Refer to the technical specifications in the Appendix for horsepower, voltage, phase,
and frequency requirements to determine the size and rating of the supply cable required.

Use the following procedure to complete the electrical connections:

1. Check to be certain that the starter heater elements correspond with the motor

requirements. If controls are not supplied, the limit switches supplied on the machine
must be wired into the circuit at the common terminal box.

2. Check that the limit switches are closed.

3. Turn switch ON at main power supply.

4. Jog the motor by pressing the START and then the OFF button. This starts and stops

the motor.

5. With the electrical power ON, check that the motor rotates in a clockwise direction at

the viewing port in the belt guard. If motor rotation is correct, continue to the next
step. If rotation is incorrect, complete the following procedure:

a. Shut power OFF and disconnect incoming power supply.

b. Reverse any two of the three power line connections to the machine.

c. Re-connect the incoming power supply line and turn ON the main power

switch to recheck motor drive rotation.

6. If an airveying system (optional) is fitted, press the Airveyor START button, and

check the blower motor rotation. The blower motor should rotate in a
counterclockwise direction. If blower motor rotation is correct, continue to step 7. If
blower motor rotation is incorrect, complete the following procedure:

a. Shut power OFF and disconnect incoming power supply line.

b. Reverse any two of the three power line connections to the blower motor.

c. Re-connect the incoming power supply line, and recheck the blower motor

rotation.

7. Allow all motors to run up to speed for at least 30 seconds.