HP ProLiant DL385 G2 Server User Manual

Page 28

Advertising
background image

Operations 28

1.

Align the PCI riser cage with the chassis and slide it into place.

2.

Tighten the thumbscrews to secure the PCI riser cage:

a.

Press down the black knob while turning clockwise, until fully tightened.

b.

While holding the black knob and pressing down, press and release the blue button to lower the

black knob to the locked position.

3.

Connect any required internal cables to the expansion board. Refer to the documentation that ships

with the expansion board.

4.

Install the access panel (on page

25

).

5.

Install the server into the rack.

6.

Connect any required external cables to the expansion board. Refer to the documentation that ships
with the expansion board.

7.

Power up the server (on page

23

).

Advertising