2 outdoors, 3 tools required, 1 tools for pole installation – Campbell Scientific T.Weather T107 Toro Weather Station User Manual

Page 13: Outdoors, Tools required, Tools for pole installation

Advertising
background image

T107 Weather Station

Securely tape box shut if transporting entire station to another site. If

at the main site, remove any communication components that are

installed at the calling computer. Repackage remaining components

for transport to field site.

Solar panel and RF items (if any) will be packed in a separate box.

Several days prior to the planned installation date…

Collect tools and site information (Section 1.3, Tools Required, and

Section 1.1, Siting and Exposure)

Install datalogger support software (Section 3, ET Software)

1.2.2 Outdoors

Locate suitable site (Section 1.1, Siting and Exposure)

Prepare concrete base (Section 2, Hardware Installation)

T107 Installation:

Place instrumentation enclosure on the ET pole. Slide enclosure to the

top of the pole and secure with correct orientation (Section 2.3,

Enclosure).

1.3 Tools Required

Tools required to install and maintain a weather station are listed below.

1.3.1 Tools for Pole Installation

ET Pole

Shovel

Rake

Open end wrenches: 3/8 in, 7/16 in, 1/2 in, (2) 9/16 in

Magnetic compass

6 ft Step ladder

Tape measure (12 ft to 20 ft)

Claw hammer

Level (24 in to 36 in)

Hand saw

Materials for concrete form:

(4) 1 in x 2 in x 12 in stakes

(2) 2 in x 4 in x 96 in lumber

(12) 8p double-head nails

(8) 16p double-head nails

20 ft form wire

1/2 Yard concrete

Concrete trowel, edger

Electrical Fish tape or 20 feet of small diameter rope

Wheelbarrow

5