23

SECTION III

INSTALLATION PROCEDURES

Installation in a proper location should be performed by competent technicians in accordance with local and

state codes. In the absence of these codes, the installation must conform to applicable American National

Standards: National Fuel Gas Code ANSI.Z223.1-LATEST EDITION and/or National Electrical Code ANSI/

NFPA NO. 70-LATEST EDITION, or in Canada, the Canadian Electrical Codes Parts 1 & 2 CSA C22.1-1990 or

LATEST EDITION.

A. REASSEMBLY OF DRYER

IMPORTANT: Always keep the tumbler (basket) section in an upright position when moving

and/or transporting.

The ML-410 dryer is shipped in two (2) pieces with the tumbler (basket) section separate from the base section.

The tumbler (basket) section will have to be lifted/hoisted onto the base section. Use cables through the eye

bolts on top of the tumbler (basket) section, or use a forklift for the lifting process.

The ML-410 tilting dryer is made with many loading and unloading options. Please refer to the reassembly

instructions on the following pages for your particular style of dryer.

If a steam dryer is shipped in two (2) pieces, the steam coil may have been removed from the top of the tumbler

(basket) section and shipped with the base section. If this is the case, carefully lift the steam coil on to the top of

the tumbler (basket) section with the steam pipe connections facing towards the right side of the dryer and bolt

the coil to the top of the dryer with the 1/4” hardware supplied. There are three (3) panels that cover the front,

right side, and rear of the steam coil. Fasten these into position also. Reconnect the steam pipe and condensate

pipe unions to the coil. These pipes run down to the flex hoses in the base section.