Installation Instructions -

Non-Permeable

Landscape

Install and Compact Base:
• Add base material 2" at a time.

• Compact each layer completely with a plate compactor or hand tamper.

• Compact to 95% proctor density (ASTM D 698).

• Be sure to compact all edges and corners thoroughly as these are at the

most risk to degradation.

• Limit any undulations to under 1/4" to limit any dips or humps in the final

installation.

Install and Level Sand Bed:
• Add a 3/4" to 1" layer of bedding

sand.

• Lay down two parallel pieces of

conduit (3/4" or 1" diameter).

• Place bedding sand between the

two pieces of conduit and pull a
screed board or straight edge down the conduit to level the sand out.

• Add sand to areas that are uneven and re-level.

• Pull the conduit out and fill in the area, leveling with a trowel or float.

• Do not compact the bedding sand.

• Refer back to page 7 for laying of AZEK Pavers.

Decide on Border / Soldier Course:
The AZEK Paver system allows for several border and soldier course
options. These can either be straight or curved. The accessory pavers can
help limit the cutting and give a finished look to the project.

INSTALL BASE MATERIAL AND SAND BED

4

IMPORTANT:
Be sure to
install base
material at the
proper slope.
This should be
approximately
1 inch over 6
feet to ensure
sufficient water
drainage.

IMPORTANT:
Do not use
sand to level
depressions in
the base layer.
Instead, add
base material to
level the area.