Mix multiple
pallets of the
same color within
an installation
to disperse any
potential slight
variations in shade.

LAYING AZEK PAVERS

+ 3” Grid

16” Grid

+

8” Grid

11” Grid

REMINDER:
Installation grids must
be orientated to allow
the pattern of pavers
to interlock grids in
both directions.

One example of cutting grids for optimal layout

Installation Instructions - All Applications

2

• Choose your starting point based on the project dimensions

and desired look, keeping in mind any cutting that may need to
happen.

• Begin by laying a handful of AZEK’s patented installation grids

in the arrangement that matches your pattern to ensure pavers
overlap grids in both directions.

• To increase installation speed, order extra installation grids to get

started.

• Bring over grids full of pavers, dump them next to where they will

be placed into the grid, and place the empty grids into place.

• If mixing colors, bring over the ratio of colors being used and

dump them in front of the person laying pavers. For example, for
a pattern using 40% Boardwalk, 40% Olive, and 20% Waterwheel.
The carrier would bring over 2 grids of Boardwalk, 2 grids of Olive,
and 1 grid of Waterwheel each time.

• Begin laying pavers in the desired pattern; ensuring pavers are

overlapping grids in both directions.

• When the edge is reached, grids can be cut to fit using a jigsaw or

miter saw, and a low tooth count wood ripping blade.

• Continue laying pavers until all full pavers (i.e. not cut or trimmed)

are installed.

• If the perimeter grid is less than 4", cut 4" or 8" off of the interior

adjacent grid to increase the size of the perimeter grid. See
example below.