Document 2.4.06, Revision 4

June 2013

Medium Power Substation Transformers

DANgER

: THE TRANSFORMER MUST BE

DE-ENERGIZED BEFORE BEGINNING ANY

MAINTENANCE WORK. FAIlURE TO DO SO COUlD

RESUlT IN SEvERE PERSONAl INJURY, DEATH, OR

PROPERTY DAMAGE.

It is the responsibility of the owner to inspect, maintain,

and keep the transformer in proper operating condition.

Report all failures during the warranty period to the

Howard Substation Transformer Division. All warranty

repairs must be made or approved by the Howard

Substation Transformer Division.

WARNINg

: TANK lEAKS MUST BE REPAIRED

IMMEDIATElY UPON DISCOvERY. FAIlURE TO

DO SO COUlD RESUlT IN SEvERE PERSONAl INJURY,

DEATH, OR PROPERTY DAMAGE.

Periodic Tests and Inspections

The following periodic tests and inspections are

recommended for routine maintenance of the

transformer.

1. Gauge readings (one month after initial

energization and annually thereafter). Gauge

readings, ambient temperature, and kvA

load should be measured and recorded. Any

abnormal reading suggests that further

diagnostic testing or inspection should be

done. If pressure/vacuum gauge and/or

fluid level gauge readings suggest a possible

tank leak, perform a pressure test according

to instructions found on Page 14 (Pre-

energization Tests and Checklist). Tank leaks

must be repaired immediately to prevent serious

damage to the transformer and danger to life.

2. Cooling fans (annual). Check the cooling fans

(if any) by setting the fan “auto/manual” control

switch to the “manual” position. The fans

should rotate at full speed within approximately

five seconds. The fans should rotate smoothly

with minimal vibration.

3. Control wiring (annual). Control wiring should be

checked to insure that wire insulation is in good

condition. The control cabinet and associated

conduit should be inspected to ensure that

weather seals are intact. Control power supply

voltage should be checked and compared to the

voltage stated on the wiring diagram.

4. Paint finish (annual). Inspect the paint finish for

damage or weathering that exposes the primer

coat or bare metal. Repair any paint damage

that might be found.

5. Fluid dielectric test (annual). Sample the

insulating fluid as described below. The

dielectric strength of the insulating fluid should

measure at least 26 kv.

6. Bushing and surge arrester insulators (annual).

Bushing and surge arrester insulators should be

clean. If the surfaces are excessively dirty, they

should be cleaned while the transformer is not

energized.

7. Bushing terminals (one month after initial

energization and annually thereafter). If the

transformer is energized and under load,

measure bushing terminal temperatures

using an infrared scanner. Excessive bushing

terminal temperature indicates a loose or dirty

connection. If the transformer is not energized,

use a torque measuring device to make sure

terminal connections are tight.

Sampling of Insulating Fluid

Transformers are filled with insulating fluid, which

provides electrical insulation within the transformer

tank and transfers heat generated in the coils to the

tank wall and radiators. The fluid is either conventional

transformer oil (mineral oil), Envirotemp

®

FR3 fluid, or

silicone fluid.

Periodically check the transformer for proper fluid level

by reading the fluid level gauge. Add fluid if necessary.

When adding fluid, add only the same type fluid that is in

the transformer.

It is also recommended that a fluid sample be drawn

annually and tested for dielectric strength. Samples

should be drawn from the bottom of the tank. Use

proper sampling procedures to prevent erroneous test

results. Dielectric strength should measure 26 kv

minimum.

MAINTENANCE

20