END FRAME ASSEMBLY

GENERAL

The end frames are symmetrical and can be used on either end. NOTE: The end frames for

the hydraulic drive are left hand and right hand.

1. Set an end frame on one of the screed

ends and align the two bottom holes

with the two holes in the edging. SeĆ

cure with two 3/8-16 X 1 whiz-lock

screws and two flange nuts (see Figure

21).

FIGURE 21

2. Attach eye bolt to clevis and place thru

hole in center of cross brace. Square

end frame with screed edging by adĆ

justing the two nuts on the eye-bolt

and then tightening them securely (see

Figure 22).

FIGURE 22

AIR DRIVE ASSEMBLY

1. Decided which end of screed the comĆ

bination regulator unit will be mounted.

2. Install 90 degree pipe fitting and nipple

on regulator end of air manifold. Install

pipe cap on opposite end of manifold.

3. Install end frames on either end of

screed, refer to End Frame Assembly.

4. On inlet side of regulator assembly

install pipe nipple and ball valve.

5. On outlet side of regulator assembly

install pipe nipple, 90 degree pipe fitĆ

ting and another pipe nipple.

6. Install pipe plug and pressure gage on

regulator assembly.

7. Install pipe rings on each side of air regĆ

ulator.

8. Using 3/8" bolts and nuts, mount air filĆ

ter assembly bracket to the screed end

bracket.

9. Using 5/16" bolts and nuts mount reguĆ

lator assembly to mounting bracket.

10.Install air hose between regulator asĆ

sembly outlet and screed air manifold.