SCREED MAINTENANCE & SERVICE

A-FRAME REPLACEMENT

REMOVAL (Mechanical)
1. Remove coupling driver. Support end

of shaft when driving out the spiral pin.

2. Loosen bearing set screws and remove

shaft. If there is a drive pulley on the

shaft, it must be loosened to remove

shaft.

3. Slightly loosen all bottom A-frame

whiz-lock screws securing edgings to

A-frames.

4. Loosen top tube bolts and remove top

tube.

5. Remove the two bottom whiz-lock

screws in A-frame to be removed. ReĆ

move A-frame.

INSTALLATION (Mechanical)
1. Installation must be done on a flat surĆ

face.

2. Loosely install new A-frame into

screed with two whiz-lock screws.

3. Loosely install top tube with hardware.
4. Tamp screed on flat surface to ensure it

is flat and true.

5. Tighten all whiz-lock screws securing

A-frames to screed edgings.

6. Tighten top tube bolts.
7. Turn and align bearings so the set

screws are all facing up.

8. Insert shaft into screed bearings. If a

drive pulley was removed, loosely

place in on shaft under engine. Also enĆ

sure shaft is threaded through drive

belt.

9. Align set screw marks in shaft with set

screws in bearings. This will ensure

shaft is properly centered in screed.

There should be an offset of 1-7/16"

from the end of the shaft to the end of

the screed edgings.

10.Tighten bearing set screws ensuring

they are all in the same orientation.

11.Align and install coupling driver.

Make sure offset of coupling driver

matches offset of eccentric bearings

when installed (thick side of couĆ

pling driver matches orientation of

thick side of eccentric bearings).
Support end of shaft when driving the

spiral pin through. The pin should be

driven in so an equal amount of the pin

is protruding from the coupling driver

on either side.

12.If applicable, tighten drive pulley and

align as described in ENGINE ASĆ

SEMBLY.

REMOVAL (Air Screed)
1. Disconnect exciter air hoses from air

manifold.

2. Remove male connectors from air manĆ

ifold.

3. Slide air manifold out of screed.
4. Slightly loosen all bottom A-frame

whiz-lock screws securing edgings to

A-frames.

5. Loosen top tube bolts and remove top

tube.

6. Remove the two bottom whiz-lock

screws in A-frame to be removed. ReĆ

move A-frame.

INSTALLATION (Air Screed)
1. Installation must be done on a flat surĆ

face.

2. Loosely install new A-frame into

screed with two whiz-lock screws.

3. Loosely install top tube with hardware.
4. Tamp screed on flat surface to ensure it

is flat and true.

5. Tighten all whiz-lock screws securing

A-frames to screed edgings.

6. Tighten top tube bolts.
7. Insert air manifold into screed. OrienĆ

tate air ports so they face up.

8. Install male connectors into air ports.
9. Connect air exciter hoses to air manĆ

ifold.