Outrigger installation, Operation – Snorkel UL40 User Manual

Page 2

Advertising
background image

2

Outrigger Installation

1. Remove the outriggers from storage locations

on sides of mast.

2. Insert into outrigger socket in base (Figure 1).
3. Push in until locking pin engages hole in end of

outrigger. Pull outward on outrigger to ensure

engagement.

4. Repeat the above steps for all other outriggers.

Make sure all four (4) locking pins are engaged.

5. Level the base, centering the bubble in the orbit

level on the base by adjusting the screwjacks at

the end of each outrigger (Figure 1). DO NOT

release the tension on an outrigger, by turning

counterclockwise, to level base.

6. All four (4) screwjack pads must be in solid

contact with a firm surface and each outrigger

indicator light must be lit before the platform

is elevated.

Operation

Before operating UL Lift insure that: the operator has

been thoroughly trained on this machine, the opera-

tor has read, fully understands and follows this

Operator Manual and the Scaffold Industry

Association's MANUAL OF RESPONSIBILITIES, the

unit has been properly set up with all four (4) outrig-

gers properly installed and the base leveled, and the

machine has passed the Safety Interlock Test.
Note: Platform will not elevate unless all four

outriggers are properly installed with screwjack

pads firmly in contact with floor and each outrig-

ger indicator lamp lit.
1. Check for external damage to the mast.
2. For AC units connect power unit plug to exten-

sion cord (12 ga. (1.5 mm²) conductor minimum

and 50 ft. (15 m) in length maximum).

Connect extension cord to properly grounded

outlet of proper voltage and frequency.

3. Turn Key to ON, Key Switch is located on the

left side of the mast (Figure 2).

4. Pull out on Lower Emergency Stop Button,

located on the left side of the mast (Figure 2), to

turn switch ON. In the event of an emergency

push the button in to cut power to all controls.

5. Enter the platform by pulling out on the locking

pin and lifting up on the upper half of the cage.

6. Lower upper half of the cage after entering

platform making sure locking pin is engaged.

7. Check that the area above the platform is clear

before elevating the platform.

8. Pull out on Emergency Stop Button, located on

platform control panel (Figure 2). In the event of

an emergency push the button in to cut power to

all controls.

9. Push both the middle and top buttons (POWER

and UP), on the Control Box (Figure 2), at the

same time to elevate the platform. Release the

buttons to stop.

10. Check that the area below the platform is clear

before lowering the platform.

11. Push both the middle and bottom buttons

(POWER and DOWN) at the same time to lower

the platform. Release the buttons to stop.

12. After use, secure unit from unauthorized use by

turning Key Switch to OFF and remove key.

Figure 1: Installing outriggers

Figure 2: Controls

Platform Controls

Base Controls

Indicator Light

Bubble Level

Locking Pin

Screwjack

Key Switch

Emergency

Stop Button

Down

Power

Up

Emergency

Lowering Valve

Optional

Emergency

Down LED

Emergency

Stop Button

Advertising
This manual is related to the following products: