3. Completed work shall be plumb and true, free of scrapes and dents. Panel ribs shall be on the module indicated in the

contract drawings within the tolerance allowed by the actual construction dimension. Excess sealant shall be
removed and touch-up paint applied to any areas where paint scrapes occur. Any panels which are badly damaged
and in the judgement of the architect cannot be repaired shall be removed and replaced.

E. Metal Soffit Panels: Provide metal soffit panels full width of soffits. Install panels perpendicular to support framing.

F. Fascia Panels: Align bottom of panels and fasten with blind rivets, bolts, or self-tapping screws. Flash and seal panels

with weather closures where fascia meet soffits, along lower panel edges, and at perimeter of all openings.

3.4

ACCESSORY INSTALLATION

A. General: Install accessories with positive anchorage to building and weathertight mounting and provid e for thermal

expansion. Coordinate installation with flashings and other components.

1.

Install components required for a complete metal roof panel assembly including trim, copings, ridge closures, seam
covers, flashings, sealants, gaskets, fillers, closure strips, and similar items.

B. Flashing and Trim: Comply with performance requirements, manufacturer’s written installation instructions, and

SMACNA’s “Architectural Sheet Metal Manual”. Provide concealed fasteners where possible, and set units true to line
and level as indicated. Install work with laps, joints, and seams that will be permanently watertight and weather resistant.

1. Install exposed flashing and trim that is without excessive oil canning, buckling, and tool marks and that is true to line

and levels indicated, with exposed edges folded back to form hems. Install sheet metal flashing and trim to fit
substrates and to result in waterproof and weather-resistant performance.


3.5

FIELD QUALITY CONTROL

A. Manufacturer’s Field Service: Engage a factory-authorized service representative to inspect completed metal roof panel

installation, including accessories. Report results in writing.

B. Remove and replace applications of metal roof panels where inspections indicate that they do not comply with specified

requirements.

C. Additional inspections, at Contractor’s expense, will be performed to determine compliance of replaced or additional work

with specified requirements.


3.6

CLEANING AND PROTECTION

A. Remove temporary protective coverings and strippable films, if any, as metal roof panels are installed, unless otherwise

indicated in manufacturer’s written installation instructions. On completion of metal roof panel installation, clean finished
surfaces as recommended by metal roof panel manufacturer. Maintain in a clean condition during construction.

B. Replace metal roof panels that have been damaged or have deteriorated beyond successful repair by finish touch-up or

similar minor repair procedures.